Posted on: August 11, 2023

[ARCHIVED] One Week Outlook - High Street (September 18th - 22nd)

Here is the 2 Week Outlook for the High Street Improvements Project for anticipated and projected work from September 18th - September 22nd. 

There will be construction at the intersection of Route 1 (Lafayette Road) and High Street, and east bound traffic on High Street at the intersection will be detoured. (Buses will be able to get through)

A_Detour planA_Businesses are open












As with any construction project, weather, unexpected delays or field conditions may change this schedule. 

Anticipated Work for the week of September 18, 2023

  • Crew 1
    • Monday - Tuesday:  Work will include drainage and sewer service installation between Marston Way and Mill Road.   
    • Wednesday - Thursday: WORK WILL INCLUDE SEWER MAIN INSTALLATION ON HIGH STREET FROM THE INTERSECTION OF ROUTE 1 (LAFAYETTE ROAD) TO TOWLE AVENUE.  
    • Friday:  Sewer main paving on High Street between Moulton Road and Mill Road.  
  • Crew 2: 
    • Monday - Thursday: Work will include drainage and sewer service installation between Moulton Road and Mill Road.   
    • Friday: Drainage and sewer service paving on High Street between Moulton Road and Mill Road.   