Here is the 2 Week Outlook for the High Street Improvements Project for anticipated and projected work form September 11th - September 22nd.
There is planned work for Saturday September 16th

As with any construction project, weather, unexpected delays or field conditions may change this schedule.
Anticipated Work for the week of September 11, 2023
- Crew 1
- Monday - Friday: Work will include drainage and sewer service installation between Moulton Road and Mill Road.
- SATURDAY: THERE WILL BE WORK ON HIGH STREET AT MARSTON WAY. THERE WILL BE LIMITED ACCESS TO MARSTON WAY.
- Crew 2:
- Monday - Wednesday: Work will include drainage and sewer service installation between Moulton Road and Mill Road.
- Wednesday - Friday: Work will include drainage installation on High Street at Springhead Lane
Projected Work for the week of September 18, 2023
- Crew 1
- Monday - Tuesday: Work will include drainage and sewer service installation between Moulton Road and Mill Road.
- Wednesday - Friday: Work will include sewer main installation between Lafayette Road to Academy Avenue.
- Crew 2:
- Monday - Friday: Work will include drainage and sewer service installation between Moulton Road and Mill Road.
Look for alternating traffic and detours. Please leave extra time to get to your destination. Be Safe!