Here is the 2 Week Outlook for the High Street Improvements Project. As with any construction project, weather, unexpected delays or field conditions may change this schedule. Below is the anticipated and projected work form August 14th -25th.
Anticipated Work for the week of August 14, 2023
- Monday - Friday: Work will include excavation and construction of the main sewer line between Moulton Road and Mill Road.
Projected Work for the week of August 21, 2023
- Monday - Friday:
- Crew 1: Work will include excavation and construction of the main sewer line between Moulton Road and Mill Road.
- Crew 2: Work will include the drainage installation between 5 Corners and Old Mill Pond Lane.
Look for alternating traffic. This means that we are planning to leave one lane open. Traffic will proceed through the one lane in an alternating pattern stopping vehicles from one direction and then the other. Please leave extra time to get to your destination. Be Safe!