Here is the 2 Week Outlook for the High Street Improvements Project.  As with any construction project, weather, unexpected delays or field conditions may change this schedule.    Below is the anticipated and projected work form August 7th -18th. 

Anticipated Work for the week of August 7, 2023

  • Monday - Friday: Work will include excavation and sewer tie-in of the main line at the intersection of High Street and Elliot Street, Taylor Street, Little River/Mace Rd and Mill Pond Lane.   

Projected Work for the week of August 14, 2023

  • Monday - Friday: Work will include excavation and construction of the main sewer line between Moulton Road and Mill Road.  

Look for possible detours if you are leaving Elliot Street, Taylor Street or LIttle RIver Road.  Roadways generally will be open with traffic control, but there will be delays. Please leave extra time to get to your destination.  Be Safe!