Department of Public Works

Posted on: July 21, 2023

[ARCHIVED] 2 Week Outlook - High Street (July 24-Aug 4)

Here is the 2 Week Outlook for the High Street Improvements Project.  Although we did not get started on the sewer line excavation, site layout, project set-up, and product submittals were ongoing.  Saw-cutting along trenches began.

As with any construction project, weather, unexpected delays or field conditions may change this schedule. Below is the anticipated and projected work form July 24th- August 4th.

Anticipated Work for the week of July 24, 2023

  • Monday -  Wednesday: Project Layout, set-up and submittals will continue. 
  • Thursday - Friday:  Work will include excavation and sewer tie-in of the main line at the intersection of High Street and Elliot Street, Taylor Street, Little River/Mace Rd and Mill Pond Lane.  

Projected Work for the week of July 31, 2023

  • Monday - Wednesday: Work will include excavation and sewer tie-in of the main line at the intersection of High Street and Elliot Street, Taylor Street, Little River/Mace Rd and Mill Pond Lane.  
  • Friday: Work will include excavation and construction of the main sewer line between Dearborn Ave. and Academy Ave.  

Roadways will be open with traffic control, but there will be delays. Please leave extra time to get to your destination.  Be Safe!